Single Dwelling Permits in Victoria

Data from 2000–2026

Single dwelling permits cover the construction, alteration, or extension of a single house on a residential lot.

Total Applications

17,816

Approved

11,755

66% of all

Refused

46

0% of all

Withdrawn / Other

6,015

Application Outcomes

Approved (11,755)
Refused (46)
Withdrawn (645)
Pending / Other (5,370)

Of 11,801 decided applications, 100% were approved.

Processing Time

25th percentile

41 days

Median

81 days

75th percentile

138 days

90th percentile

202 days

75% of single dwelling permits are decided within 138 days. Based on 1,233 applications with complete date records.

Single Dwelling Permits by Council

CouncilApplicationsApprovedRefusedWithdrawnMedian Days
Hobsons_Bay3,2183,151048
Murrindindi2,6412,3843157
Moorabool1,9750017
Strathbogie1,3411,235882
Benalla947908027
Pyrenees79076700
Mornington_Peninsula70341611496
Yarra_Ranges523000
Yarra51719112
Nillumbik439145423
Kingston31160154
Glen_Eira291000
Greater_Geelong284227117
Surf_Coast276213015
Casey247125103176
Maroondah215000
Whittlesea2039101731
South_Gippsland18013208
Latrobe175136117
Whitehorse171121423
Wellington1641421551
Moonee_Valley15815800
Golden_Plains154117215
Frankston150000
Bass_Coast1327828
Merri-Bek126111212
Darebin12473111
Manningham115330049
Monash1117403
Mitchell110000
Melbourne1085701
East_Gippsland10810400167
Maribyrnong913603112
Indigo865619
Boroondara814304
Bayside62452680
Alpine604204
Ararat564902
Greater_Dandenong52390085
Hume48000
Northern_Grampians393502
Swan_Hill372900
Queenscliffe353400
Towong331906
Stonnington262600
Wyndham24000
Southern_Grampians231601
Gannawarra211600
Horsham14901
Buloke121110
Brimbank8000

Most Common Zones

Zones where single dwelling permits are most frequently lodged.

Frequently Asked Questions

What are the outcomes for single dwelling permit applications in Victoria?

Of 17,816 single dwelling applications tracked across 51 Victorian councils, 11,755 were approved and 46 were refused. An additional 645 applications were withdrawn. Among decided applications, 100% were approved.

How long does a single dwelling permit take to process?

The median processing time for single dwelling permits across Victoria is 81 days from lodgement to decision. 75% of applications are decided within 138 days. Processing times vary significantly between councils.

Which council processes the most single dwelling permits?

Hobsons_Bay has the highest volume with 3,218 single dwelling applications.

Check single dwelling permit history for your property

Enter any Victorian address to see planning permit history, zoning controls, overlays, and development potential.

Search your property

Based on 17,816 single dwelling applications from 51 councils (2000–2026). Outcome rates are calculated from decided applications only (excludes pending and withdrawn). Data sourced from council planning registers.