Multi-unit Permits in Victoria

Data from 2000–2026

Multi-unit development covers the construction of two or more dwellings on a single lot, including townhouses, apartments, and dual occupancy projects.

Total Applications

13,924

Approved

9,484

68% of all

Refused

79

1% of all

Withdrawn / Other

4,361

Application Outcomes

Approved (9,484)
Refused (79)
Withdrawn (541)
Pending / Other (3,820)

Of 9,563 decided applications, 99% were approved.

Processing Time

25th percentile

55 days

Median

124 days

75th percentile

201 days

90th percentile

295 days

75% of multi-unit permits are decided within 201 days. Based on 1,649 applications with complete date records.

Multi-unit Permits by Council

CouncilApplicationsApprovedRefusedWithdrawnMedian Days
Hobsons_Bay5,8555,5821157
Glen_Eira1,110000
Bayside909684177981
Monash5913571237
Casey5543642328174
Kingston543216431
Moonee_Valley50850300
Darebin404165520
Merri-Bek295258328
Moorabool288008
Greater_Geelong235151120
Manningham2339300116
Whitehorse227119750
Strathbogie174159113
Yarra_Ranges159000
Yarra1558201
Mornington_Peninsula1556507148
Frankston154000
Benalla13512105
Nillumbik1284626
Greater_Dandenong1259000220
Maribyrnong1062003137
Whittlesea1003706106
Latrobe856614
Boroondara812005
Maroondah65000
Hume62000
Wellington46310950
Surf_Coast442507
Brimbank39000
Bass_Coast352114
Pyrenees282700
East_Gippsland282800181
South_Gippsland271702
Wyndham25000
Queenscliffe242100
Melbourne23801
Mitchell21000
Murrindindi201601
Alpine201400
Golden_Plains171103
Indigo16704
Horsham14901
Swan_Hill121100
Stonnington9810
Northern_Grampians9601
Ararat9800
Southern_Grampians7600
Gannawarra6500

Most Common Zones

Zones where multi-unit permits are most frequently lodged.

Frequently Asked Questions

What are the outcomes for multi-unit permit applications in Victoria?

Of 13,924 multi-unit applications tracked across 49 Victorian councils, 9,484 were approved and 79 were refused. An additional 541 applications were withdrawn. Among decided applications, 99% were approved.

How long does a multi-unit permit take to process?

The median processing time for multi-unit permits across Victoria is 124 days from lodgement to decision. 75% of applications are decided within 201 days. Processing times vary significantly between councils.

Which council processes the most multi-unit permits?

Hobsons_Bay has the highest volume with 5,855 multi-unit applications.

Check multi-unit permit history for your property

Enter any Victorian address to see planning permit history, zoning controls, overlays, and development potential.

Search your property

Based on 13,924 multi-unit applications from 49 councils (2000–2026). Outcome rates are calculated from decided applications only (excludes pending and withdrawn). Data sourced from council planning registers.