Easement Permits in Victoria

Data from 2000–2026

Easement applications involve the creation, variation, or removal of easements on land titles.

Total Applications

611

Approved

441

72% of all

Refused

4

1% of all

Withdrawn / Other

166

Application Outcomes

Approved (441)
Refused (4)
Withdrawn (24)
Pending / Other (142)

Of 445 decided applications, 99% were approved.

Processing Time

25th percentile

45 days

Median

63 days

75th percentile

99 days

90th percentile

195 days

75% of easement permits are decided within 99 days. Based on 66 applications with complete date records.

Easement Permits by Council

CouncilApplicationsApprovedRefusedWithdrawnMedian Days
Hobsons_Bay19919600
Murrindindi514308
Casey31251263
Strathbogie272403
Moorabool26001
Whitehorse191611
Glen_Eira18000
Benalla181601
Kingston17201
Greater_Geelong171401
Yarra_Ranges15000
Mornington_Peninsula15140161
Darebin151101
Whittlesea1470011
Moonee_Valley121200
Merri-Bek10901
Pyrenees8800
Nillumbik8001
Melbourne8200
Frankston7000
Bayside742061
Bass_Coast7500
Yarra6001
Mitchell6000
Boroondara6300
Stonnington5500
Latrobe5401
Hume5000

Most Common Zones

Zones where easement permits are most frequently lodged.

Frequently Asked Questions

What are the outcomes for easement permit applications in Victoria?

Of 611 easement applications tracked across 28 Victorian councils, 441 were approved and 4 were refused. An additional 24 applications were withdrawn. Among decided applications, 99% were approved.

How long does a easement permit take to process?

The median processing time for easement permits across Victoria is 63 days from lodgement to decision. 75% of applications are decided within 99 days. Processing times vary significantly between councils.

Which council processes the most easement permits?

Hobsons_Bay has the highest volume with 199 easement applications.

Check easement permit history for your property

Enter any Victorian address to see planning permit history, zoning controls, overlays, and development potential.

Search your property

Based on 611 easement applications from 28 councils (2000–2026). Outcome rates are calculated from decided applications only (excludes pending and withdrawn). Data sourced from council planning registers.