Earthworks Permits in Victoria

Data from 2000–2026

Earthworks permits cover excavation, filling, and other ground-level changes, particularly on sloping sites or in overlay areas.

Total Applications

201

Approved

93

46% of all

Refused

4

2% of all

Withdrawn / Other

104

Application Outcomes

Approved (93)
Refused (4)
Withdrawn (5)
Pending / Other (99)

Of 97 decided applications, 96% were approved.

Processing Time

25th percentile

75 days

Median

114 days

75th percentile

199 days

90th percentile

276 days

75% of earthworks permits are decided within 199 days. Based on 31 applications with complete date records.

Earthworks Permits by Council

CouncilApplicationsApprovedRefusedWithdrawnMedian Days
Moorabool42000
Yarra_Ranges24000
Murrindindi191701
Casey191121172
Strathbogie181701
Nillumbik15300
Hobsons_Bay141400
Mornington_Peninsula1251176

Most Common Zones

Zones where earthworks permits are most frequently lodged.

Frequently Asked Questions

What are the outcomes for earthworks permit applications in Victoria?

Of 201 earthworks applications tracked across 8 Victorian councils, 93 were approved and 4 were refused. An additional 5 applications were withdrawn. Among decided applications, 96% were approved.

How long does a earthworks permit take to process?

The median processing time for earthworks permits across Victoria is 114 days from lodgement to decision. 75% of applications are decided within 199 days. Processing times vary significantly between councils.

Which council processes the most earthworks permits?

Moorabool has the highest volume with 42 earthworks applications.

Check earthworks permit history for your property

Enter any Victorian address to see planning permit history, zoning controls, overlays, and development potential.

Search your property

Based on 201 earthworks applications from 8 councils (2000–2026). Outcome rates are calculated from decided applications only (excludes pending and withdrawn). Data sourced from council planning registers.